PMBC approves multiple payments and change orders; receives updates on Juliet Long HVAC and roof projects
The Ledyard Permanent Municipal Building Committee met October 6, 2025 (Town Hall Annex, hybrid). Members reviewed roof punch‑list items at the BOE Central Office and Gales Ferry, discussed a delayed Eversource cutover for Juliet Long School, and received a positive financial update on the Juliet W. Long (JWL) HVAC project (projected $545,000 savings). The Committee approved a series of invoices, payments and change orders for roof and HVAC work (including a $46,035 payment to Gold Seal Roofing and a $294,025 application for payment to The Nutmeg Companies), authorized an RFQ/RFP for a commissioning agent for the JWL HVAC project, and voted on multiple consultant and testing invoices. One small consultant invoice (Silver Petrucelli Inv#25-1933, $149.40) received no action.