The committee unanimously approved five project invoices totaling $2,199,153.16. Polson HVAC work remains on schedule for staff returning August 24 and is trending about $100,000 under the guaranteed maximum price, although the electrical shutdown and cutover depend on finalizing an easement.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Most work needed before staff return is scheduled to be completed by August 24, including replacement of all 43 penthouse units. The VRF heating and cooling systems are expected to be fully online by mid-October, with some units coming online in September. Roof concept estimates were $5,982,828 for Polson and $3,728,758 for DHHS; the DHHS project must advance through capital planning and budget referendum processes for both projects to proceed toward summer 2028 construction.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.