The Polson project was reported to be on its original schedule and under its original guaranteed maximum price. The committee unanimously approved an $11,976 credit and invoices totaling $1,445,599.90.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Work is advancing on the electrical systems, gym improvements, and VRF heating and cooling installation, with 90% of indoor cassette units installed. The generator is expected in October, while penthouse and auditorium work is scheduled to begin June 22. The committee also approved a change that avoids lead-paint chemical stripping in the gym weight room.