The LP Wilson BOE restroom improvements project was reported about one week behind schedule and 22.87% complete. Commissioners approved a $128,250 payment to Millennium Builders, a $1,135 electrical change order, and two additional project invoices totaling $3,497.50; each vote passed 5-0-0.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Work on the LP Wilson restroom project is progressing, but it is currently about one week late. Officials said they are addressing disagreements over Millennium Builders’ cost and time estimates while directing work to continue. The commission also approved payments for several HVAC, construction, engineering, and asbestos-monitoring projects, including $48,070 for LP Wilson HVAC Phase 3.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.