The committee reported that the project’s remaining budget is very tight, with a cooling tower correction estimated at about $250,000 and consultants needing proposals for additional services. HVAC repairs were expected to take one to two weeks, followed by testing, balancing, and two to four weeks of commissioning.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Work continues to resolve problems with the school’s refrigerant-based VRV HVAC units and other closeout items. Interior punch-list work is complete, but one exterior item and several site items remain. The committee approved $14,022 in invoices and requested a February 9 special meeting to review the project’s finances and next steps.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.