The Board authorized a Notice of Intent to Award the School Road and Skippack Pike intersection improvement project for $1,017,127, subject to bid-document review. Construction is anticipated to begin in April and finish before winter weather, with the project primarily funded through a PennDOT Multimodal Grant.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The intersection project is moving toward construction at a bid amount below the anticipated $1.5 million construction budget. Whitpain Township is expected to contribute approximately 23% of total construction costs, while grant funding covers most of the project. The Board also directed staff to continue evaluating participation in a renewable electricity purchasing partnership and authorized advertising an updated 2021 International Fire Code ordinance.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.