Quick context to catch up fast.
The Cat Rock water tank and Wellesley Street pump station are both projected to reach 100% design completion by mid-October 2026. The tank project’s 90% plans are expected in May, followed by approximately two and a half months of MassDEP review.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Design work for the Cat Rock tank is nearly complete, with review comments due by April 1 and final design documents expected in May. The project schedule also incorporates the water-main easement work between Route 117 and Cat Rock, while the longer transmission main through Route 20 was eliminated. The board said it will respond within the next week to questions raised by Michael Chasan about the Cat Rock tank.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.