The joint committee approved four major change orders totaling up to $190,126, including geothermal revisions, electrical coordination, EV panel modifications, and roof repairs, and authorized up to $18,000 for foundation damp-proofing work.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The approvals allow additional construction work to proceed on the library building project. The foundation item was approved as Option 3 with an $18,000 spending limit while the team reviews related trade impacts and the full scope. Previously executed change orders totaled $397,267.09.