Quick context to catch up fast.
The FF&E/Technology Subcommittee recommended that the Permanent Building Committee approve the proposed technology budget with a 5% contingency. The budget lists $1,793,777.15 in technology costs against a $1.8 million budget, or $6,222.85 under budget before the added contingency.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The Wakefield Memorial High School project’s technology plan is moving toward review by the Permanent Building Committee. The recommendation covers equipment and related technology needs for about 1,000 students. The committee also unanimously approved the March 5 working group minutes; no final approval of the technology budget is recorded in the provided excerpts.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.