The committee unanimously approved four Wakefield Memorial High School project invoices totaling $9,991,719.88, including a $9,699,631.38 construction payment.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The approvals authorize payment for construction administration, construction work, and testing services on the Wakefield Memorial High School project. The project had committed 92% of its total budget, with $21,619,327 remaining uncommitted as of the end of December 2025. Construction was progressing on science lab casework, Media Center windows, masonry, exterior sunshades, and roofing.