Council unanimously approved a $308,666 contract with Fillmore Construction LLC to install a 14-by-4-foot box culvert providing primary access to the new Public Works Facility at 810 Northwoods Boulevard. Construction is pending final permits from the U.S. Army Corps of Engineers and FEMA.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The approved project will add a large drainage crossing needed to provide primary access to the new Public Works Facility. The contract price was the lowest of five bids, which ranged from $308,666 to $434,000. Work cannot begin until required permits are secured.