Quick context to catch up fast.
The Board unanimously approved an $1,850 change order for the SUM-East Avenue Phase 1 project, raising the contract total to $370,050. The additional cost covers assessments of additional parcels for right-of-way acquisition, and the meeting minutes state that this portion is 100% funded.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The approved change increases the amount paid to O.R. Colan Associates, LLC for acquiring property rights needed for the East Avenue project. The change was approved 5-0, and the minutes state that the project portion is fully funded.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.