A propane tank incident led to a weekend job-site shutdown and a safety reset, with the committee reporting an expected delay of about 1.5 weeks. Tanks will be arranged differently, and the committee approved $946,160.44 in project-related invoices plus a $500 donation.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Construction was temporarily stopped after a propane tank incident, and the tanks will be set up in a different manner before work resumes. The delay is expected to add about 1.5 weeks to the project schedule. The committee also approved several invoices and reported a projected contingency amount of $1,137,872.