The committee unanimously approved a $37,411.23 payment for the Tootin’ Hills roof project, releasing the retainage that had delayed project closeout and the application for state reimbursement.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The payment allows the roof project to move toward closeout while preserving the Town’s ability to pursue recourse over the unresolved roof issue. The committee also reported that the Simsbury Meadows Performing Arts Center band shell expansion was nearly complete, with an as-built survey still pending and two $777 testing invoices approved.