The committee approved change orders creating a $12,650 credit for the Simsbury Meadows Performing Arts Center band shell expansion, while rejecting three other proposed changes. Structural steel is complete, construction is advancing, and the project is projected to finish July 3, 2026.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The band shell project remains on schedule, with framing, decking, and plumbing underway. The committee approved changes that reduce project costs by $12,650 and approved $293,902.81 in related project payments and invoices. A future shower can be accommodated through current plumbing and bathroom changes, but the shower installation itself will require a separate project.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.