The commission voted 5-0 to authorize the chair to sign the Gate 3 Taxi Lane grant application when received. Runway 6-24 reconstruction is expected to cost a little over $6 million, with 95% covered by the FAA, while the Gate 3 project is estimated at about $850,000.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The airport is moving ahead with major pavement and taxiway improvements. The Runway 6-24 grant has been received, so contracts and project submittals can proceed, although no construction start date was set. The Gate 3 Taxi Lane project had its pre-bid meeting, with bids scheduled to open June 17.