The existing runway reconstruction project received a low bid of slightly more than $5 million, compared with an estimate of slightly more than $7 million; the commission is awaiting a grant offer before proceeding.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The project would rebuild the existing runway using updated pavement-thickness standards. The taxi lane project is targeted for bidding by May 22, with a bid opening planned for June 17. The commission also approved hiring a UMass organization to search for a new airport manager and approved the May 17 flour drop.