The Sewerage Authority unanimously approved a $155,760.92 partial payment for the sludge thickening system improvements project, representing approximately 92% of the contract amount.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The payment covers work completed on the sludge thickening system, although weather has delayed recent construction and tank coating work. The Authority also continued planning for improvements at Pumping Stations 4 and 5 and began filming sewer and storm drains ahead of road paving. No members of the public commented.