The authority unanimously voted 4-0 to recommend a $78,230.66 rink roof repair project, with work preferably beginning in mid-May.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The proposed work will reinforce the cooling tower, clean and epoxy-coat supporting steel, and repair the surrounding roof. The cooling tower would not need to be removed or taken out of service, and the project’s ladder would be secured so customers cannot access it. Additional roof repair costs may be needed if further damage is found.