The committee reported that Phase 1 is complete, Phase 2 is underway, and Wings 3 and 4 opened for staff and students. Members unanimously approved $643,392.90 in Payment Application 8, $23,613.37 in change orders, and three invoices totaling $31,486.87.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Construction is progressing at John Wallace Middle School, with work beginning on Wing 6 and punch-list items continuing from Phase 1. The committee approved more than $698,000 in project payments and changes, all unanimously. The project update also noted that the state reimbursement had been processed.