The commission moved to apply for an ODOT grant to remove trees near Runway 5, with grant applications due June 1. A separate ramp expansion grant application totals $85,500, with $81,225 from the FAA and $4,275 from ODOT, and is due May 1.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The airport is seeking outside funding for safety and facility improvements, including tree removal and ramp expansion. The commission also reported that the Taxilane B design project received FAA closeout approval, allowing final reimbursement requests to proceed. Twenty-one applicants remain on the hangar wait list.