Exterior steel work was expected to be substantially complete that week, but five exterior panels damaged by the Department of Public Works must be replaced, with the timeline impact still unknown.
Browse all related coverage for the main local project pages tied to this summary.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Construction is progressing, with under-floor electrical and plumbing work underway and exterior wall framing planned for the end of March. The project is also addressing water main and electrical service installation, including possible additional costs for service cables. The committee did not report a final schedule or cost change.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.