Lancaster reported that it has completed half of the projects required under its amended wastewater permit and is ahead of schedule. The permit extends the compliance period 10 years, with the final required project due by December 1, 2033.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The city is progressing on projects intended to reduce combined sewer overflows and improve wastewater infrastructure. Lancaster is working with Ohio EPA to revise the timing of three projects related to CSO 1029 while using monitoring results and sewer-model updates to determine whether those projects are needed.