The committee approved four utility-related contracts, including a $780,489 sanitary sewer rehabilitation project and a $2,194,480 storm sewer rehabilitation project. Staff said the storm sewer work was expanded to include future planned improvements, with the overall program estimated at about $200,000 over the 2025 budget but offset by savings in the low bid.
Committees mentioned
Open the committee coverage hubs tied to this summary.
Topics discussed
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
What this means
Hoffman Estates moved forward with repairs and maintenance for its underground water and drainage systems. The committee approved work on sanitary sewers, storm inlets, and storm sewers, plus extra construction inspection services. For residents, these projects are meant to help reduce sewer problems, improve drainage, and keep the system in better working order. One storm sewer project was expanded to include work planned for future years, and staff said the added cost is about $200,000 above the 2025 budget.
Key decisions
Follow the major takeaways from this briefing.
- Approved a contract with National Power Rodding for the 2025 Sanitary Sewer Rehabilitation Project, not to exceed $780,489.
- Approved a contract with Visu-Sewer of Illinois, LLC for the 2025 Storm Inlet Cleaning Project, not to exceed $55,100.
- Approved a contract with Visu-Sewer of Illinois, LLC for the 2025 Storm Sewer Rehabilitation Project, not to exceed $2,194,480.
- Approved a supplemental agreement with BLA, Inc. for construction inspection services, adding $82,225 for a total not to exceed $246,805.
Timeline & follow-ups
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Meeting information
Details and records from this meeting.
Public Works & Utilities Committee
Agenda
- 1. CALL TO ORDER/ROLL CALL
- 2. APPROVAL OF MINUTES
- A. Public Works & Utilities Committee 11-24-2025attachments=1Decision: APPROVAL OF MINUTES
- 3. PUBLIC COMMENT
- 4. NEW BUSINESS
- A. Approval of a Resolution authorizing a contract with National Power Rodding of Chicago, IL, for the 2025 Sanitary Sewer Rehabilitation Project in an amount not to exceed $780,489attachments=2 | reports=1Decision: NEW BUSINESS
- B. Approval of a Resolution authorizing a contract with Visu-Sewer of Illinois, LLC of Bridgeview, IL, for the 2025 Storm Inlet Cleaning Project in an amount not to exceed $55,100attachments=2 | reports=1Decision: NEW BUSINESS
- C. Approval of a Resolution authorizing a contract with Visu-Sewer of Illinois, LLC of Bridgeview, IL, for the 2025 Storm Sewer Rehabilitation Project in an amount not to exceed $2,194,480attachments=2 | reports=1Decision: NEW BUSINESS
- D. Approval of a Resolution authorizing a Supplemental Agreement with BLA, Inc. of Itasca, IL, for construction inspection services in the amount of $82,225 for a total not to exceed amount of $246,805attachments=2 | reports=1Decision: NEW BUSINESS
- 5. REPORTS
- A. Public Works Department Monthly Reportattachments=1Decision: REPORTS
- B. Engineering Division Monthly Reportattachments=1Decision: REPORTS
- 6. PRESIDENT'S REPORT
- 7. ITEMS IN REVIEW
- 8. OTHER
- 9. ADJOURNMENT
Documents from this meeting
- Agendahttps://hoffmanestatesil.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1364,plainText=false)
- Packethttps://hoffmanestatesil.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1365,plainText=false)
- Minuteshttps://hoffmanestatesil.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=2524,plainText=false)
Recent documents
Fresh records from this municipality.
Civic leadership
Know who to contact about the decisions that matter.