The committee advanced a ComEd underground power line agreement for the Compass data center site and approved two Higgins/Hassell TIF actions tied to redevelopment of Lot 8 and the rest of the district. One of those TIF items passed with one no vote.
Projects mentioned
Browse all related coverage for the main local project pages tied to this summary.
Committees mentioned
Open the committee coverage hubs tied to this summary.
Topics discussed
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
What this means
The committee recommended a license agreement that would let ComEd install underground electric lines through several rights-of-way to support the Compass data center site. It also approved a redevelopment agreement and TIF note for Lot 8 in the Higgins/Hassell area, with up to $8 million in reimbursable TIF funding tied to the project and a March 1 purchase deadline for the developer. In a separate action, the committee approved a new TIF note for the rest of the Higgins/Hassell district after removing Lot 8, changing the revenue split to 75% for the developer and 25% for the village after administrative costs. The Lot 8 redevelopment item was sent to the Village Board without a recommendation, and the other TIF note passed 5-1.
Key decisions
Follow the major takeaways from this briefing.
- Recommended approval of a ComEd license agreement for underground electric distribution lines in the Chatham Drive, Essex Drive, Beacon Pointe Drive, Beverly Road, and Trillium Boulevard rights-of-way.
- Approved a Lot 8 redevelopment agreement and TIF note for the Higgins/Hassell Redevelopment Project Area, with maximum reimbursement of $5 million for Phase 1 and $3 million for Phase 2.
- Sent the Lot 8 redevelopment item to the Village Board without a recommendation for action next week.
- Approved a new TIF note for the Higgins/Hassell Redevelopment Project Area except Lot 8, with one dissenting vote.
- Changed the remaining Higgins/Hassell TIF revenue split to 75% developer and 25% village after administrative costs.
Timeline & follow-ups
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Meeting information
Details and records from this meeting.
Planning, Building & Zoning Committee-Special
Agenda
- 1. CALL TO ORDER/ROLL CALL
- 2. PUBLIC COMMENT
- 3. NEW BUSINESS
- A. Approval of a License Agreement with Commonwealth Edison Company (ComEd) for underground electric distribution lines in the Chatham Drive, Essex Drive, Beacon Pointe Drive, Beverly Road, and Trillium Boulevard Rights-of-Wayattachments=1 | reports=1Decision: NEW BUSINESS
- B. Approval of an Ordinance Authorizing the Execution of a Lot 8 Redevelopment Agreement and the Issuance of a TIF Note for Lot 8 in the Higgins/Hassell Redevelopment Project Area in the Village of Hoffman Estates, Illinois (Higgins/Hassell TIF District)attachments=2 | reports=1Decision: NEW BUSINESS
- C. Approval of an Ordinance Authorizing the Issuance of a TIF Note for Higgins/Hassell Redevelopment Project Area Except Lot 8attachments=1 | reports=1Decision: NEW BUSINESS
- 4. OTHER
- 5. ADJOURNMENT
Documents from this meeting
- Agendahttps://hoffmanestatesil.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1316,plainText=false)
- Packethttps://hoffmanestatesil.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1317,plainText=false)
- Minuteshttps://hoffmanestatesil.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=1363,plainText=false)
Recent documents
Fresh records from this municipality.
Civic leadership
Know who to contact about the decisions that matter.