The pool project’s apparent low bid was $7,896,000, leaving $654,000 in contingency within the $8,550,000 authorized funding. The committee also awarded Golf Now the golf reservation-system contract for $10,000 annually.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The pool project is currently within its approved funding, although several items were removed from the bid to meet the budget. Construction Dynamics submitted the lowest apparent bid, but the minutes do not state that a final contract award was made. The committee also approved several donation requests, reported 259 golf permits issued with $708,929 in sales, and reviewed the proposed $2,610,509 FY2027 operating budget.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.