The project’s 100 percent design documents were submitted for a 45-day review, with construction expected to begin in August 2027 and continue for 30 months.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The Route 3A project has reached a major design milestone and is now being reviewed by MassDOT. The task force voted to support a 2026 Annual Town Meeting warrant article that would help the Select Board pursue proposed Article 97 land-use legislation at the state level. Engineers are also developing right-of-way plans, environmental permits, wetland mitigation, and a construction communications plan for residents.