The committee reviewed changes intended to keep the pool project within its $8.55 million budget, with subcontractor bids due February 4 and general contractor bids due February 18.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The pool project is being adjusted before contractors submit bids, including making the spray deck an optional add-on. The committee also received a financial report showing December revenue of $173,967.22 and expenses of $135,622.01. A new golf-course reservation vendor will be sought because the committee expects the change to increase revenue.