Window installation at the West Freehold Schoolhouse is expected to finish within a week, with $1,100 in installation savings from the original bid. Painting is expected to begin around June 30, 2026, while a reopening is tentatively being considered for October or early spring 2027.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The schoolhouse restoration is progressing, with new windows nearly finished and painting planned next. New shutters will be paid for with Open Space money, and the commission will seek pricing for deck work and door refinishing. A reopening date has not been set.