The Island Strategic Action Committee (ISAC) met Jan. 6, 2026. Members approved the Nov. 2, 2025 minutes, received ex‑officio updates (including a Nueces County TIRZ #2 payment approval and seawall funding discussion), reviewed engineering schedules (beach access road 6–7 months; OPCC to accompany JFK Causeway 60% design), and deferred the Bond 2026 resolution draft to February. Beach permit stickers are ready for sale and the Billish Park skatepark design remains with Engineering.