Commissioning of the new Concord Middle School was reported as roughly 90% complete, with additional testing planned during February vacation. The committee also reviewed $605,902.52 in recent project expenditures, bringing total spending to $103,852,327.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The school project is in its final testing and correction phase. After February testing, WSP will prepare a punch list identifying remaining items for review. The committee reviewed three change orders totaling $111,092.45, but the minutes do not state that the committee voted on them.