The water line project had about 7,200 feet installed at an average pace of 150 feet per day, with $148,115 spent on capital projects through April. The Authority also reported that remaining federal funds must be spent by September 30, 2026, and continued investigating the Struble tank leak.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Construction of the water distribution line is progressing faster than the well project, while the booster station work remains on schedule. The Authority is reviewing the Struble tank after an initial leak test was inconclusive. The meeting minutes do not report a confirmed service disruption or final leak determination.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.