The committee unanimously approved six change orders totaling up to $191,257 for the New Norton and New North End school projects, including stormwater compliance work, electrical service changes, classroom call stations, and construction adjustments.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The approvals authorize additional construction spending for two new school projects. The largest costs were $87,439 for new electrical-service directives at the New North End School and up to $65,000 for updated stormwater permits and monitoring at both schools. The committee also received the third state payment for the North End School project and the second payment for the Norton School project.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Details and records from this meeting.
Fresh records from this municipality.
Know who to contact about the decisions that matter.