Quick context to catch up fast.
The committee unanimously approved $67,935.97 in construction changes, including interior finishes, porch construction, and additional sprinkler coverage. It also approved a $43,612 transfer from contingency funds to administration and a $182,752.72 contractor payment.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
The fire substation project is about 38% complete, with $4,965,311 spent and $8,081,946 remaining to finish. The approved changes address building finishes and sprinkler requirements, while the budget transfer covers additional administrative and borrowing costs. Construction was moving from the administrative area toward the apparatus bay, with roof work awaiting a break in the weather.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.