Quick context to catch up fast.
The committee unanimously approved Change Order #6 for $32,358.47, covering site, conduit, traffic-signal, and training-tower work. A no-cost schedule extension moves substantial completion from the end of November to the second week of December 2026.
Open the committee coverage hubs tied to this summary.
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
Construction is progressing, with about 75% of the structural steel installation complete and second-floor decking planned for early February. The approved change order adds $32,358.47 to the project for several construction changes, partly offset by a $7,707.53 utility-conduit credit. The project team reported no current concerns about delayed materials.
Follow the major takeaways from this briefing.
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.