Finance Committee approves funding and contracts
At a glance
Quick context to catch up fast.
The committee recommended approval of a $590,008 bridge contingency, a $649,489 utilities network contract, and a $119,000 wastewater treatment plant bridge improvements contract, while also advancing a SISP grant agreement for Badger Avenue signal work and a 2026 purchasing policy update.
Committees mentioned
Open the committee coverage hubs tied to this summary.
Topics discussed
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
What this means
The committee backed several spending and contracting items that would support street, bridge, utility, and wastewater projects in Appleton. It also recommended accepting a state grant and signing the related financial agreement for signal rehabilitation and retrofits on Badger Avenue. A mid-year budget report for Legal and Administrative Services was presented, but no action was taken on that item.
Key decisions
Follow the major takeaways from this briefing.
- Recommended approval of a SISP grant award and State-Municipal Financial Agreement for Badger Avenue signal rehabilitation/retrofits.
- Recommended approval of using $590,008 in 2026 Bridge CIP funds as contract contingency for the Olde Oneida Street Bridge over South Mill Race reconstruction project.
- Recommended approval of the 2026 Purchasing Policy.
- Recommended approval of awarding the Appleton Wastewater Treatment Plant M-K Tunnel Bridge Improvements Project contract to Staab Construction Corporation for $119,000 with a 10% contingency, not to exceed $130,900.
- Recommended approval of awarding the Appleton Department of Utilities Network Improvements Project to Van Ert Electric for $649,489 with a 7.5% contingency, not to exceed $698,201.
Timeline & follow-ups
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Meeting information
Details and records from this meeting.
Finance Committee
Agenda
- Call meeting to order
- Pledge of Allegiance
- Roll call of membership
- Approval of minutes from previous meeting
- July 6th, 2026 Meeting Minutes
- Public Hearing/Appearances
- Action Items
- Request to accept grant for Hwy 125 (College Av) / Badger Av & Hwy 47 (Memorial Dr) / Badger Av - Signal Rehabilitation & Retrofit.
- Request to accept SISP Grant Award and approve State-Municipal Financial Agreement (SMFA) for Badger Avenue Signal Rehab/Retrofits.
- Request to approve use of $590,008 in 2026 Bridge CIP funds as contract contingency for Olde Oneida Street Bridge over South Mill Race Reconstruction Project.
- Request to approve the 2026 Purchasing Policy.
- Request to award Appleton Wastewater Treatment Plant M-K Tunnel Bridge Improvements Project contract to Staab Construction Corporation in the amount of $119,000 with a contingency of 10 percent for a total project cost not to exceed $130,900.
- Request to award Appleton Department of Utilities Network Improvements Project Base Bid and Allowance to Van Ert Electric, in the amount of $649,489 with 7.5% contingency of $48,712 for project total not to exceed $698,201.
- Information Items
- 2026 Legal and Administrative Services Mid-Year Budget Report.
- Adjournment
- Request to approve the 2026 Purchasing Policy.